单项选择题Using Oracle Scheduler you have scheduled two jobs, JOB_Aand JOB_B, to run at 9:00 p.m. every Friday. You want both the jobs to use a single resource plan, WEEKEND_PLAN. Which task must have already been performed to enable you to achieve this objective?()

A、 A window must have been created with the WEEKEND_PLAN resource plan.

B、 A program must have been created with the WEEKEND_PLAN resource plan.

C、 A job class must have been created with the WEEKEND_PLAN resource plan.

D、 A window group must have been created with the WEEKEND_PLAN resource plan.

  • C