试题详情
单项选择题 (1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity. 空白(3)处填()

A、F-S

B、F-F

C、S-F

D、S-S

  • D
  • 关注下方微信公众号,在线模考后查看

热门试题