试题详情
- 单项选择题 A financial customer has three data centers that are approximately five kilometers apart. Their SAP application data needs to be kept synchronized within 10 milliseconds between the three sites. Which of the following solutions satisfies the customer's recovery time objective?()
A、DS8700 systems at each site running Metro Mirror
B、DS5300 systems at each site running Metro Mirror
C、DS5100 systems at each site running Global Mirror
D、XIV systems at each site running synchronous mirroring
- A