单项选择题 You are working on the cost budget for one project. Which of the following is true()

A、This process assigns cost estimates to project activities including risks and contingency plans.

B、The cost baseline will be used to measure variances and future project performance.

C、This process assigns cost estimates for expected future period operating costs.

D、The cost baseline is the expected cost for the project.

  • B