- 单项选择题The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()
A、Data flow model
B、The project critical path
C、Resource loading chart
D、WBS (Work Breakdown Structure)
- B
关注下方微信公众号,在线模考后查看
热门试题
- A computer’s onboard
- Which of the followi
- One end of a CAT5 ca
- When configuri
- A system
- Which of
- Shortly after&
- Which of the followi
- Which of
- An administrat
- Which of the followi
- Which of
- An administrator is
- Which of the followi
- An environment
- A user states that
- An administrat
- Which of the followi
- Which of the followi
- Click the