单项选择题If the organizational spending plan has allocated $100,000 for a project, and the high level budget estimate for that project is $200,000; which of the following is accurate?()

A、The high level budget estimates are inaccurate

B、The organizational spending plan is inaccurate

C、The budget is not aligned with the spending plan of the organization

D、The detailed bottom up budget will need to be adjusted

  • C